The walkthrough shows rail laying, frame erection and drive commissioning for the 15.6-inch smart terminal system — exactly the sequence the documents below record.

Technical Documents · Installation

The paper trail a site actually generates.

Five stages, each closing with the document that signs it off. Collect the set and the job is provably done — missing forms are how commissioning stalls on the last day.

Floor rails and shelving frames erected during mobile compactor installation
Stage by stage

From lorry to acceptance certificate.

Every stage below lists the forms it produces. They are the installation document pack your facilities team files — and the evidence the warranty depends on.

01
Delivery & unloading

Off-load and condition check

Frames, rails and drives are off-loaded against the packing list and inspected for transit damage before they enter the room.

Packing listDamage reportGoods receipt
02
Site handover

Floor and readiness record

The floor is checked for flatness and load capacity and the access route is confirmed clear before any frame is set down.

Floor flatness recordLoad capacity sign-offAccess route check
03
Rail & frame erection

Anchored and levelled

Rails are laid to tolerance, frames are erected, and every fixing is torqued to the anchor plan. The as-built layout is recorded from the actual positions.

Anchor plan (as-built)Torque logLevelling record
04
Shelving & drive commissioning

Loaded and tested

Shelves are fitted, drives are powered and each run is exercised. A load test confirms behaviour at capacity and the wiring is recorded as built.

Load test recordWiring diagram (as-built)Run test sheet
05
Acceptance & handover

Signed and filed

The acceptance certificate closes the job, the O&M file is handed over, and operators are trained on chapters 01–04 of the manual.

Acceptance certificateO&M fileTraining record
Typical schedule

How long a standard room takes.

Durations are for a typical archive room of 20–40 runs with two skilled crews. Larger or access-constrained sites scale the erection and commissioning stages.

StageWhat happensCrew
01 DeliveryOff-load and condition check against the packing list.2
02 Site handoverFloor flatness, load sign-off and access route confirmation.2
03 Rail & frameRail laying, frame erection, torque log and levelling record.3–4
04 CommissioningShelf fit, drive power-up, load test and as-built wiring.2–3
05 AcceptanceCertificate, O&M handover and operator training (ch 01–04).2
Before we arrive

Four conditions the site must meet.

Installation pauses — and the schedule slips — when one of these is wrong. Confirm them at handover and the crew works straight through.

01

Floor flatness

Rail runs need a flat, level slab within tolerance; uneven floors stop rails seating and shake the run at speed.

02

Power supply

Electric and smart drives need the agreed supply and an accessible point per run before commissioning starts.

03

Ceiling clearance

Top shelf plus handling height must clear the ceiling, lights and any sprinkler heads along every run.

04

Access route

Frames are long and rigid; doors, lifts and corridors on the path from lorry to room must take the longest section.

Acceptance

What the certificate signs off.

The acceptance certificate closes the job. Every item below is confirmed on site and recorded in the installation pack — miss any one and the warranty clock does not start.

Mechanical
  • All runs travel full stroke and seat home square
  • Rail torque log within the anchor plan
  • Levelling record within floor tolerance
  • Load test passed at rated capacity
Electrical
  • Supply point per run confirmed and labelled
  • Drives exercise cleanly at each speed
  • Photocells and safety edges stop travel
  • As-built wiring diagram recorded
Documentation
  • Packing list and goods receipt matched
  • Damage report clear or resolved
  • Acceptance certificate signed
  • O&M file handed to the facility team
Training
  • Operators trained on chapters 01–04
  • Default login changed and verified
  • Training record signed and filed
  • Service contacts entered in the terminal